What is Earned Value PMI?

What is Earned Value PMI?

Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports. Oftentimes the term “earned value” is defined as the “budgeted cost of worked performed” or BCWP.

What are the four Earned Value Management forecasting formulas?

Earned Value Management contains four calculations which give the project manager a forecast into future performance of the project: Estimate to Complete (ETC) Estimate at Completion (EAC) Variance at Completion (VAC)

What is Earned Value Management in Projects?

Earned value management (EVM) is a project management methodology that integrates schedule, costs, and scope to measure project performance. Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly.

How do you calculate earned value in project management?

The Formula for Earned Value (EV) The formula to calculate Earned Value is also simple. Take the actual percentage of the completed work and multiply it by the project budget and you will get the Earned Value. Earned Value = % of completed work X BAC (Budget at Completion).

What is earned value formula?

Earned value represents the amount of the work that’s actually completed. It’s the value the project has produced. As mentioned earlier here is the formula to calculate the earned value: EV = Percent complete (actual) x Task Budget.

What is CPI and SPI in project management?

The Cost Performance Index (CPI) is defined as the ratio of Earned Value to Actual Cost, while the Schedule Performance Index (SPI) is defined as the ratio of cumulative Earned Value to cumulative Planned Value (PMI, 2000). Both CPI and SPI are traditionally defined in terms of the cumulative values.

How is Earned Value Management implemented?

Implementing Earned Value Management in a Design Consultancy

  1. Establish a project work breakdown structure.
  2. Establish a project schedule.
  3. Calculate and baseline Planned Revenue.
  4. Track Earned Revenue and Actual Effort.
  5. Track project performance and adjust Earned Revenue.

How do you do earned value Management?

The 8 Steps to Earned Value Analysis

  1. Determine the percent complete of each task.
  2. Determine Planned Value (PV).
  3. Determine Earned Value (EV).
  4. Obtain Actual Cost (AC).
  5. Calculate Schedule Variance (SV).
  6. Calculate Cost Variance (CV).
  7. Calculate Other Status Indicators (SPI, CPI, EAC, ETC, and TCPI)
  8. Compile Results.

What is SPI in project management?

The schedule performance index (SPI) is a measure of the conformance of actual progress (earned value) to the planned progress: SPI = EV / PV. When CPI or SPI are greater than 1.0, this indicates better-than-planned project performance, while CPI or SPI less than 1.0 indicates poorer-than-planned project performance.

What is the SPI in EVM?

Difference between Cost Performance Index (CPI) and Schedule Performance Index (SPI):

Cost Performance Index Schedule Performance Index
CPI = Earned Value / Actual Cost SPI = Earned Value / Planned Value
If CPI is less than 1 then project is over budget. If SPI is less than 1 then project is behind schedule.

What do you need to know about Earned Value Management?

Earned value management (EVM) is one of several project management techniques you can use to estimate where you are currently in a project versus the project’s schedule and budget. EVM provides visibility into whether or not you’re on track to finish the project within the established cost and timeline baselines defined in the project plan.

Can You do earned value analysis on any project?

The point is that you can do earned value analysis calculations on any project, but unless you have complete earned value management in use on your project, it will be extremely unlikely to obtain correct results. In order to easily use EVM, your organization really needs to have an earned value management system in place.

What are the goals of the PMI initiation phase?

PMI’s PMBOK explains the goals of the initiation phase as follows: “the key purpose of this Process Group is to align the stakeholders’ expectations with the project’s purpose, give them visibility about the scope and objectives, show how their participation in the project and its associated phases can ensure that their expectations are achieved.”

What does PMI process Group 5 edition mean?

Now it’s time to follow your plan. PMBOK 5th edition states that this PMI process group “involves coordinating people and resources, managing stakeholder expectations, as well as integrating and performing the activities of the project in accordance with the project management plan.” In other words, do your plan.

Posted In Q&A