What are standard schedule rates?

What are standard schedule rates?

Standard Data Book. SCHEDULE OF RATES. Definition: In order to determine the rate of a particular item, the factors affecting the rate of that item are studied carefully and then finally a rate is decided for that item.

How are civil works rates calculated?

The rate of particular item of work depends on the following:

  1. Specifications of works and material about their quality, proportion and constructional operation method.
  2. Quantity of materials and their costs.
  3. Cost of labours and their wages.
  4. Location of site of work and the distances from source and conveyance charges.

What is DSR rate?

The latest version of Delhi Schedule of Rates (DSR) shall be the basis for preparation of estimate. The rates entered in the estimates should generally agree with the scheduled rates, but where due to any reason, the later are not available, market rates may be considered.

Is code for rate analysis?

Rate analysis of RCC (Reinforcement Cement Concrete) used for reference book IS Code 1200 part 2 (IS Code 1200 part 2 used for measurement), IS Code 2212, and CPWD Part 1.

How does a schedule of rates work?

A schedule of rates is a table of rates for specific activities that can be used to negotiate commercial terms when the broad activities are known but not the precise quantities. Schedule of rates contracts lend themselves to be used in two different situations. See also Contract, Time and Materials.

Who prepare schedule of rates?

A schedule or list of rates of various items is prepared after the analysis of rates of these items. Such a document is known as the schedule of Rates or S.O.R. It is prepared by large concerns or public bodies such as Central Public Works Department (CPWD), State Governments etc.

What percentage of total cost is added to the schedule of rate of the public work department for overhead cost?

10 % of the total cost is added to the schedule of rates of the public work department for over-head cost.

How do you prepare a rate?

Here we are giving some simple tips to prepare rate analysis to start your project.

  1. 1st Step to know Constant by Mix design report.
  2. 2nd step to know wastage of material in percentage, here we need to consider 2 types of wastage.
  3. 3rd step to know the all rates like material, labor, machinery, overheads, etc.

What is district schedule rates in civil engineering?

The schedule of rates consists of groups of items such as demolishing items, excavation items, concrete items, RCC works, brickwork items etc. and also information regarding the present wages of labour and prices of different items, is given in it.

What is SSR in civil engineering?

Standard Schedule Of Rates (SSR) – Best Civil Engineer.

Who prepare the schedule of rates?

What do you infer from schedule of rates?

SOR means Schedule of Rates. Prevailing market rates of each particular item. The quantities can be easily worked out by an engineer based on the drawings and specifications. The rates would however, vary from place to place depending upon the rates of construction materials, labour, working environment etc.

How are rates determined for civil engineering works?

Analysis of Rates for Civil Engineering Works. In order to determine the rate of a particular item, the factors affecting the rate of that item are studied carefully and then finally a rate is decided for that item. This process of determining the rates of an item is termed as analysis of rates or rate analysis.

How big is the CPWD schedule of rates?

The CPWD schedule of rates contains the basic rates of materials, labour, carriage etc. of about more than 2500 items and the finished rates of about 3000 items of works covered under different subheads like Building work, Concrete work, water supply etc.

How are labour charges calculated for government works?

The labour charges can be obtained from the standard schedule of rates 30% of the skilled labour provided in the data may be taken as Ist class, remaining 70% as II class. The rates of materials for Government works are fixed by the superintendent Engineer for his circle every year…

What is the cost of construction material in India?

What is the construction material cost in India in 2021? TMT or TMX Steel Price- 42 to 55 Rs. Per Kg Aggregate Price- 1600 to 3300 Rs. Per Tonne RMC Price- 3000 to 7500 Rs. As per grade of Concrete Bricks: 6 to 10 Rs. per Piece.

Posted In Q&A