(8)No person may engage in any construction or cause or allow such construction to occur, in a residential area−(a)before 07h00 and after 18h00 from Monday to Saturday; and(b)at any time on any Sunday or public holiday, except−(i)under circumstances where such construction is necessary in order to preserve property or …
Where do the building regulations apply?
The regulations apply to new construction work, and do not require that existing buildings are brought up to standard. However, where new work is being carried out to existing buildings, such as alterations, extensions, loft conversions, window replacement, insulation and so on the regulations do apply.
How long does building regs take?
You can expect a decision within 5 weeks, or 2 months with your consent. You’ll get a completion certificate within 8 weeks of completion of the building work as long as it complies.
Do you need Neighbours permission to build?
In terms of the NBA, unless it states otherwise in another law, neighbors do not have the right to object to building plans. In certain cases, however, the municipality may invite neighbors to object to the building plans.
Can you complain about Neighbours construction?
Although it is recommended that you first try to resolve any problems by talking the issue through with your neighbour, or by using mediation, your local council has a duty to investigate noise from a building project if it is deemed to be damaging to health or a nuisance, known as a statutory nuisance.
What was National Building Regulations and Building Standards Act 1995?
The National Building Regulations and Building Standards Amendment Act 49 of 1995 intends: to empower a local authority to accept the appointment of certain persons registered in terms of the Engineering Profession of South Africa Act, 1990, to carry out certain work; and to provide for matters connected therewith.
How many parts are in SANS 10400 building regulations?
As there are a total 23 Parts to the SANS 10400 Building Regulations we have divided them into three sections to improve the ease of navigation. The order in which the different Parts of the regulations are displayed follows the same order as the regulations themselves as they are published.
Do you need planning permission for a temporary building?
There is an article about “temporary buildings” and the NBR HERE. Perhaps that will answer your question. Lorna you will need planning permission relating to zoning, and you will need approved plans for all construction work. This must be done by a competent person who will need to oversee all building work.
What are the regulations for a parking garage?
The regulation that you are asking about is SANS 10400 Part-C, you can read what we say here: size-dimensions-room-height A parking garage is classed in SANS 10400 Part-A as a J4 occupancy (Occupancy used for storing or parking of more than 10 motor vehicles).