While you might be tempted to skip a transfer switch when installing your generator, the truth is that it is almost a mandatory part of owning and using a backup power source. The only real choice you have is to use a manual switch or an automatic one.

Does a generator need a disconnect?

As a general rule, generators must be equipped with a disconnecting means that can be locked in the open position. As well, the disconnecting means must be able to disconnect the generator, all protective devices and control apparatus entirely from the circuits supplied by the generator.

How much clearance does a generator need?

Clearance from the ends and front of the generator should be 36 inches. This would include shrubs, trees and any kind of vegetation. Clearance at the top should be a minimum of 48 inches from any structure, overhang or projections from the wall.

What is prime mover shutdown?

When in use, the prime mover or engine can be shut down so that it cannot be restarted without a manual or mechanical reset of the generator start circuits. If there should be an emergency, pushing the stop button or the off switch will immediately shut down the generator.

How far should a generator be from a gas meter?

If possible, place your generator near both the electric and gas meters; In most cases, generator distance from property line should be at least 5 feet; Your unit should be at least 18 inches from your home; and.

Where does 445.18 ( a ) require disconnecting means?

N (C) Generators Installed in Parallel. Where a generator is installed in parallel with other generators, the provisions of 445.18 (A) shall be capable of isolating the generator output terminals from the paralleling equipment. The disconnecting means shall not be required to be located at the generator.

What does 445.18 mean in NFPA 70?

Once there, click on their link to free access to the 2017 NEC edition of NFPA 70. 445.18 Disconnecting Means Required for Generators.

What are the NEC requirements for branch circuits?

NEC Part II provides requirements for branch-circuit calculations and for specific types of branch circuits. Part III covers the requirements for feeder and service calculations, using what’s commonly called the “standard method of calculation.”

What do I need to know about NEC Article 220?

220 Introduction to Article 220—Branch-Circuit, Feeder, and Service Calculations This five-part article focuses on the requirements for calculating the minimum size of branch circuit, feeder, and service conductors. Part I describes the layout of Article 220 and provides a table of where other types of load calculations can be found in the NEC