What is resource dependent activity in Primavera?
The Resource Dependent activity derives its working days, and therefore its duration, based upon the calendars of resources assigned to it. Simply put, if the resource has some non-working period in their calendar, the activity will also be non-working during that time.
What is task dependent activity in P6?
Task Dependent: This type of activity indicates that assigned resources should be scheduled based on the activity’s calendar, rather than the calendars of the resources. Resource Dependent: This type of activity indicates that resources should be scheduled based on their assigned calendars.
What are the different activity types in Primavera?
Activity Types and Milestones in Primavera P6
- Finish Milestone.
- Level of Effort.
- Resource Dependent.
- Start Milestone.
- Task Dependent.
- WBS Summary.
How many types of activities are there in P6?
There are six types of activities in Oracle Primavera P6 and they can be added to a project schedule by using several ways.
What is relationship in Primavera?
Relationships can either be a driving relationship or a non-driving relationship. In Primavera P6, driving relationships specify the start date of the successor. Non-driving relationships do not specify the start date of the successor. Let’s assume that you have a sample project schedule with 4 activities.
What is level of effort in Primavera?
A “Level of Effort” Activity in Primavera P6 is a special activity type with unique qualities for duration. Primavera P6 will calculate the duration of a Level of Effort Activity based on dates from its predecessor(s) and successor(s).
What are the different types of resources allowed by Primavera?
Anyone familiar with Primavera P6 understands that there are three types of resources: labor, nonlabor, and material.
What are milestones in Primavera?
Milestones are zero-duration activities in project plans, useful for showing key moments in a project. Primavera P6 treats milestones a little differently than other project and portfolio management applications.
How do you count activities in P6?
Activity Count in Primavera P6
- Add the Column “Activity Count” to your Activity layout. This is a simple column with a value of “1” in each activity field.
- Turn off any Filters and Group by WBS.
- Note the totals for the column “Activity Count” for the project and for each phase or WBS level.
What is float in Primavera?
In Primavera P6, there are two important values: Total Float and Free Float. Total Float: is the amount of time an activity can be delayed without delaying the Project Finish Date. Free Float: is the amount of time an activity can be delayed without delaying its Successor Activity Finish Date.
How many types of relationships are available in Primavera?
four types
Primavera P6 EPPM provides up to four types of relationships allowing you to model activities both in series and parallel.
What is a hammock in P6?
A hammock is an activity that hangs between two activities in a schedule. In connection to Level of Efforts in Primavera P6, a hammock can also be used to convey overhead resources and costs like project management efforts and quality inspections for a certain area of the schedule without affecting the whole project.